Automated poultry plant growing in three phases from 4,000 to 12,000 birds/hour: siting and site plan

A landowner with a large plot wants an automated plant that starts at a capacity suited to today's market and grows in phases to 12,000 birds/hour. The site plan gives every phase its place from the start, so expansion is added with no demolition and no crossing routes.

Phase 1Phase 2Phase 3Staff housingRendering and wastewater

Drag to rotate; use two fingers to zoom and move.

Conceptual model with no dimensions: pick a phase to see what is built in it; dotted buildings are reserved for later phases from day one, so expansion needs no demolition.
FacilityAutomated poultry plant expanding in phases
Capacity4,000, then 6,000, then 12,000 birds/hour
CountrySaudi Arabia
LandA part carved out of a large plot, within the boundary to be licensed
Also on siteStaff housing and services in a separate zone
DeliverablesArea and phasing report, a scaled site plan sheet, and a CAD version

The challenge

The owner has a large plot and only needs enough of it for the plant. The questions before any drawing: where does the plant sit within the land? How much area does it need today and in years to come? How is each phase added without demolishing the last or blocking the next? And where do the staff live, away from odour and noise?

What I did

Reading the land and siting the plant

  • Matching the land sketch with its coordinates and orientation, and fixing the part suitable for the plant within the boundary to be licensed.
  • Choosing the corner of the site by the prevailing wind, the shortest access from the planned streets, and room to expand.
  • Carving out only the area the final phase needs, and leaving the rest of the land for the owner's other uses.

Three phases in one plan

  • Three capacity scenarios, 4,000 then 6,000 then 12,000 birds/hour, each with its own buildings and areas.
  • The production building extends with each phase along the same flow, so the line never reverses and dirty and clean zones never cross.
  • Utilities, rendering and wastewater sited for the final phase, downwind of housing and offices.
  • A detailed area schedule for each phase, and an implementation plan in phase order.

Staff housing on site

  • The plot was widened to hold a separate housing zone on one side and production on the other, with a buffer between them.
  • A separate housing gate, away from the live-bird gate and the by-product route.
Whole plotAllocated part within the licensed boundaryStaff housingservices, mosqueOffices, parkingPhase 14,000 bphPhase 26,000 bphPhase 312,000 bphUtilitiesgrow with each phaseRenderingWastewaterCold stores, dispatchexpand with capacityLive-bird receivingand holding shedProduct gateBirds + wheel washHousing gatePrevailing wind: away from housingN
Conceptual site plan: the plant's allotted area within the whole plot, housing in its own zone, the production building extending with each phase along the same flow, and rendering and wastewater downwind of housing.

Conceptual drawing to show the method, with no dimensions.

Deliverables

  • A report with the area schedule for each phase and the implementation stages.
  • A site plan sheet at true scale, with building sizes and proposed heights.
  • A CAD version of the plan, as the basis for the detailed drawings.

The outcome

  • The owner knows where the plant sits on his land and how much area each phase needs.
  • Expansion became planned steps from day one, not surprise decisions after construction.
  • He has a clear basis for the detailed drawings and for licensing.

Scope of work

Land sketch and coordinates checkPlant sitingCarving out the needed areaThree capacity scenariosArea schedule per phaseImplementation stagesStaff housing on siteRoute and gate separationScaled site plan sheetCAD file

Common questions

Is it better to start small and expand, or build full capacity at once?

Starting smaller lowers capital and risk until the market is proven, provided the space, routes and utilities for later phases are reserved from day one. Without that, expansion means demolition and rebuilding.

How is the plant area chosen from a large plot?

Carve out what the final phase needs, with roads and setbacks, on the side with the shortest access, keeping rendering and wastewater downwind of housing.

Can staff housing be inside the plant site?

Yes, in a separate zone divided from production by a buffer, with its own gate, and away from the bird holding area, rendering and wastewater.

What should be reserved for later phases from the start?

The extension of the production building and cold stores, roads and truck routes, and the sites for utilities, the by-product unit and wastewater, so each phase is added without a long stop or demolition.

Have land and thinking of a poultry plant?

Ask your question on WhatsApp. Technical questions are welcome, with no obligation.

Ask on WhatsApp

More work

Project data belongs to its owner; only the scope and method are shown. Terms and privacy