Poultry processing plant of 10,000 birds/hour on two lines: from the site plan to infrastructure sheets for every contractor

A 10,000 birds/hour poultry processing plant split over two parallel lines of 5,000 each. The whole project was designed: where each building sits on the land, where each machine sits on the line, down to the last drain channel and power point the contractor needs before the equipment arrives.

123456789101112

Drag to rotate; use two fingers to zoom and move.

Conceptual model of the project with no dimensions: the site with its buildings, the production complex with both lines and equipment, and the product route from live birds in to product out. Drag to rotate, pinch to zoom.
  1. 1Live bird receiving and crate wash
  2. 2Production hall (two lines)
  3. 3Water and air chilling
  4. 4Grading, cut-up and packing
  5. 5Chilling, freezing and storage
  6. 6Chilled loading dock
  7. 7Live bird holding shed
  8. 8Utilities
  9. 9Administration and lab
  10. 10Staff housing
  11. 11Rendering
  12. 12Wastewater treatment
FacilityPoultry plant with two parallel production lines
Capacity10,000 birds/hour: two lines × 5,000 (80,000 birds in an 8-hour shift)
CountrySaudi Arabia
SlaughterHalal by knife, no stunning
ProductChilled and frozen, whole birds and cuts
ChillingWater then air, on each line
FlexibilityEach line ready for added equipment later, with no demolition
Design conditionsAmbient temperature up to 50°C

The challenge

The investor wants 10,000 birds/hour and chose two lines instead of one: if a line stops for maintenance the other keeps running, and in slow seasons one line runs at lower cost. What he needed was not just a site plan but a complete file from which each contractor takes his own sheet and works without guessing, with each line able to be upgraded later by adding equipment, without demolition or re-routing services.

What I did

Site plan

  • Buildings arranged on a one-way route from dirty to clean, with the prevailing wind: housing and offices upwind, rendering and wastewater downwind.
  • Separate gates for live birds, for product, and for staff and housing.
  • Roads wide enough for articulated trucks to turn, checked by tracing their swept path, without taking any space from the buildings.
  • A holding shed for live birds with drive-through lanes, fans and misting, with housing kept well away from it and from odour sources.
  • A compliance table checking every item of the plan against the official requirements for slaughterhouses and factories.

Layout of the two lines and equipment

  • Line speed, stage lengths and crew per station were calculated, then a geometric simulation checked clearances, bend radii and worker access.
  • Receiving on a single-level U-shaped crate conveyor right in front of the hangers, with a crate washer and stacker after it, and two docks per line, unloading then clean-crate loading, so the truck never moves.
  • A time gap between batches from different farms on the line, so each batch stays identified and traceable.
  • Pneumatic and vacuum tools in evisceration, and an in-line automatic grader by weight class.
  • Water chilling then two-tier air chilling on each line, which cut the chill room footprint sharply without shortening chilling time.
  • A dividing wall crossed only by the shackle line, emergency doors between the two halls, and space, supports and service openings reserved in evisceration for equipment added later.
Cold& freezingPackinggrade, cut-upChillingwater, then airEvisceration& inspectionUpgrade reserveKill & pluckbleed, scaldReceivingU crate lineL1Packinggrade, cut-upChillingwater, then airEvisceration& inspectionUpgrade reserveKill & pluckbleed, scaldReceivingU crate lineL2Service aisle and emergency doors between linesShared utilities and servicesLive birds inPacked product outBlood, feathers: own routeDividing wall
Conceptual production layout: two parallel lines, each running one way from receiving to packing, a wall between the dirty and clean zones, a shared cold store, and space reserved in evisceration for later upgrades.

Conceptual drawing to show the method, with no dimensions.

Chilling, freezing and storage

  • Every product leaves the production hall packed and wrapped before it enters any cold room.
  • Blast freezing in baskets, then cartoning, because cartons slow freezing and break down with moisture.
  • Freezing time, the blast room cycle, frozen store occupancy and truck waiting time at the dock were all calculated.
  • Central refrigeration on Freon, because its servicing, technicians and spares are readily available locally.

Infrastructure sheets: one for each contractor

  • Builder's works: shackle line supports and beams, equipment bases, wall and roof openings, and insulated freezer floors with ventilation to stop the ground freezing below.
  • Drainage: separate industrial and sanitary networks, with channels and covers sized, levelled and set out from the walls. Blood and feathers never enter the drains; they are collected and moved on their own route.
  • Water and washdown: a full plant water balance, a network for each zone, and a central pressure-washing system with fixed stations.
  • General power: panels, feeders, cable routes and sizes, and lighting and sockets set out, excluding equipment wiring done by the line supplier.
  • Refrigeration and ventilation: an air pressure cascade from clean to dirty rooms, fresh-air units, local extraction over scalders and pluckers, and condensate drainage.
  • Each sheet shows its own trade clearly, with the others faded for coordination only, so no contractor's route clashes with another's.
Builder's worksDrainageWater and washdownPower and lighting+++−− −Refrigeration and ventilationLine and equipment layoutEach contractor gets his own trade sheet; other trades appear faded for coordination only
One sheet per trade: the same building on every sheet, carrying one trade's network only, with clear setting-out.

Illustration of how the sheets are split, with no dimensions.

Checking before handover

  • A 24-hour hydraulic simulation of the drains, including tank dumps and cleaning at worst case, which led to upsizing pipes that would have filled and re-sloping the feather channel to carry its load.
  • Every crossing between drainage, water, power and structure was checked so no pipe meets a footing or a cable.
  • An independent check of the structural calculations by a different method found two beams needing a larger section, and they were changed.
  • Value engineering: point-by-point lighting design per room, instead of a blanket estimate, cut the lighting load by over a quarter at the required light level.

The outcome

  • A complete design file: site plan, two-line layout, chilling and freezing, a large master sheet, and a layered CAD version.
  • Each contractor receives his sheet with clear dimensions and specifications, and can start structure and services before the equipment arrives.
  • Flexible running: one line or two depending on the season, and later upgrades by adding equipment in spaces reserved from the start.

Scope of work

Site planTruck routes and turningCompliance checkTwo-line layoutLine and crew calculationsChilling, freezing and storageBuilder's worksDrainage networksWater and central washdownGeneral power and lightingRefrigeration and ventilationSimulation and clash checksValue engineeringLayered CAD file

Common questions

Why two lines of 5,000 instead of one of 10,000?

Flexibility: if one line stops for maintenance the other keeps running, in slow seasons one line runs at lower cost, and each line can be upgraded on its own. The price is more floor space and a slightly larger crew than one line of the same capacity, so the choice depends on the size and swings of the market.

Which sheets does the contractor need before the line arrives?

Builder's works (supports, bases, openings), drainage with channels and levels, water and washdown points, general power and lighting, and refrigeration and ventilation. Best as one sheet per trade, set out from the walls.

Why must blood and feathers stay out of the drains?

They block channels and pipes and overload the treatment unit. Blood is collected in a tank and feathers are moved on their own route to the by-product unit.

Why freeze in baskets and carton afterwards?

Cartons insulate the product and slow freezing, and they get damp and break down in blast rooms. Basket freezing is faster and cleaner, with cartoning afterwards.

Can a line be upgraded later without a long stop or demolition?

Yes, if it is designed for it from the start: reserved space, supports rated for the added machines, and spare openings and services in place. Then the upgrade is installation, not rebuilding.

Planning a poultry plant with one line or more?

Ask your question on WhatsApp. Technical questions are welcome, with no obligation.

Ask on WhatsApp

More work

Project data belongs to its owner; only the scope and method are shown. Terms and privacy